Jacksonville and Northeast Florida

Federal construction scheduling for Jacksonville contractors

We provide Primavera P6 scheduling and delay support for contractors pursuing and performing federal work in Jacksonville and Northeast Florida. Baselines, cost loading, monthly updates, narratives and time impact analyses are built to the scheduling section incorporated into your contract.

Written scope and flat fee. Quote back within one business day.

PSP certified Primavera P6 Built to your scheduling section AACE RP 52R-06 AACE RP 29R-03 DCMA 14-point
Federal work in Northeast Florida

The scheduling section runs the job

Northeast Florida has the USACE Jacksonville District, NAVFAC Southeast, NAS Jacksonville and Naval Station Mayport. On that work the scheduling section in your contract decides what you submit, who reviews it, and what it takes to get paid and get time. The agencies don't all ask for the same thing, so the first job is reading the section you actually signed.

NAVFAC

Navy and Marine Corps work

NAVFAC's current section, UFGS 01 32 17.00 20, covers cost-loaded network analysis schedules and calls for native P6 XER deliverables. Confirm which version made it into your contract. The cost loading has to tie to the contract line items.

USACE

Corps of Engineers work

USACE jobs commonly carry UFGS 01 32 01.00 10. Expect activity coding, cost loading and update rules spelled out in the section, with an SDEF export to RMS where the contract requires it. QC and the schedule have to tell the same story.

VA

Veterans Affairs work

VA major projects under 01 32 16.13 require an independent CPM consultant and a Network Analysis Schedule tied to progress payments. Small projects under 01 32 16.15 allow qualified in-house scheduling.

When the VA requires an independent consultant →

Side by side on submittals, reviews and RMS: federal schedule specs compared →

Bid to closeout

Where we come in on a federal job

We can pick up at any point. The earlier we read the section, the fewer surprises at the first review.

01

Before and after award

We read the scheduling section and list what it requires: scheduler qualifications, the preliminary and baseline submittal dates, cost loading, update cycle, narratives, file formats and meetings. You get the scheduling scope to carry in your bid, and after award a submittal plan that hits the dates.

02

Baseline development

Government reviews, submittals, procurement, construction, testing, commissioning and closeout, all logic-linked to the contract milestones. Review durations come from the contract, not wishful thinking. Cost loading ties to the CLINs or pay items so the first pay app isn't the first fight. P6 baseline development →

03

Monthly reporting

Progress pulled from the QC reports and the field, remaining durations that match the crews on site, critical path changes explained, and the cost-loaded progress report where the section requires one. The narrative says what moved and why. Monthly updates and narratives →

04

Changes and disputes

Fragnets inserted into the right pre-impact update, a TIA per AACE RP 52R-06, and the records that back it. If the modification doesn't settle it, the same record supports an REA, and forensic analysis per AACE RP 29R-03 if it goes further. Schedule movement alone doesn't prove entitlement. Notice, responsibility and concurrency still decide it. Fragnets and TIAs on federal jobs →

Operating installations

Base access is a schedule input, not an excuse

Work inside an active base or federal campus runs slower than the same work on an open site. If the baseline assumes a full shift and free access, every update fights the plan. We put the restrictions in the logic so a lost day has a cause the reviewer can see.

01Access and badging. New workers and subs need time to get cleared. We carry that lead time ahead of each trade's start instead of assuming crews show up ready
02Escorts and restricted areas. Escort availability and secure spaces cut productive hours. Durations reflect the real working window
03Restricted deliveries. Gate inspections and delivery windows affect long-lead equipment and concrete. Delivery activities sit in the schedule, not in someone's notebook
04Work areas and utility outages. Area releases and outage requests go through the installation with their own lead times. Each outage is an activity with its request, approval and work window
Federal experience

Federal schedules we have run

Relevant federal experience. Project locations are identified where disclosed. Names withheld, references on request.

VA · Independent CPM consultant

VA medical center, Virginia

Independent CPM consultant under the VA Network Analysis Schedule spec. NAS compliant baseline, cost loading and monthly updates tied to progress payments.

USACE · Lead scheduler

Harbor pump station and dissolved oxygen system, Savannah, GA

Lead scheduler on a large USACE environmental mitigation project. NAS compliant baseline with CLIN cost loading and balancing, SDEF export to RMS as that contract required, TIA change order reviews and @Risk modeling.

Federal campus

High-containment laboratory on a federal campus

Monthly updates and schedule review.

More on agency work: federal scheduling consultant →

Jacksonville FAQ

Questions from federal contractors

Does every federal job need an independent scheduling consultant?
No. It depends on the scheduling section in your contract. VA major projects under section 01 32 16.13 call for an independent CPM consultant. VA small projects under 01 32 16.15 allow qualified in-house scheduling. USACE and NAVFAC sections set their own scheduler qualifications and submittal rules, so read yours before you price the work. If your own scheduler can meet it, we can support them instead of replacing them.
Do we have to export our schedule to RMS?
Only where the contract requires it. Some USACE contracts call for an SDEF export to RMS. NAVFAC's current section calls for native P6 XER files. We build to whatever your section actually says and check the export before it goes in.
Our baseline came back disapproved. Can you fix it?
We start with the review comments and the section, not a rebuild. Comments usually trace back to logic gaps, constraints, missing cost loading or activities that don't line up with the specification. We correct the schedule and write a response to each comment for the resubmittal. Approval is still the government's call, so we make the response easy to check.
How do we get time on a federal modification?
Show it in the schedule. We insert a fragnet for the change into the update in effect before the impact and measure the effect on the completion date. The contracting officer has to be able to follow the logic, so the fragnet, the source documents and the narrative go in together. Cost goes in the proposal separately.
Are you based in Jacksonville?
No. We are based in Seminole County in Central Florida. Federal schedule work is mostly done from the files, and we come to the site or the government meeting when the work calls for it.

Related: REAs and claims · DCMA 14-point check · forensic delay analysis

Elsewhere in Florida: Florida overview · Orlando · Tampa Bay · Miami

Bidding or running federal work in Northeast Florida?

Send the scheduling section from your solicitation or contract. We'll tell you what it requires and quote the scheduling scope. If a call helps, 20 minutes is enough to scope the work.