Time impact analysis for GCs: how to justify a time extension that holds up

A time extension request holds up when it rests on a credible network, the contemporaneous update, a real fragnet and honest concurrency. Anything less gets pulled apart by the owner's consultant.

CPM Predictive Solutions·7/2/26·7 min read

When an owner change, design delay or other excusable event hits, justify the time with a prospective TIA per AACE RP 52R-06: build a fragnet for the event, insert it into the update in effect when it occurred, and let the recalculated network show the effect on completion. If the critical path moves, you have a supported request in CDs, subject to the contract, responsibility, concurrency and notice. If it only consumes total float, you have a documented impact but, under most contracts, no extension yet. Expect the owner's scheduling consultant to review every piece.

Why this matters more for the GC than anyone

You hold the completion date, and it usually carries liquidated damages. Every unrecovered owner delay comes out of your float first and your pocket second. Skip contemporaneous TIAs and you're self-funding the owner's changes, then facing the LD conversation with no record. TIA discipline isn't claims posturing. It's how the time side of the contract gets administered, change by change.

What the analysis stands on

  • A credible network. A TIA is only as good as the schedule it runs in. Open ends, constraint-driven dates and a critical path that ignores slips let the owner's reviewer dismiss your result unread. Run the DCMA 14-point check on your own schedule first and fix the network.
  • The right base schedule. The update with a data date just before the event, statused honestly. Measuring from the baseline or an after-the-fact schedule misstates the impact and reads as manipulation.
  • A real fragnet. The activities and logic of the change itself (revised drawings, resubmittals, procurement, added or resequenced work), tied in where it connects. One "owner delay" bar at your requested duration is an argument, not an analysis. Source every duration from submittal logs, vendor quotes or production rates.
  • Honest concurrency. Address your own performance issues that ran alongside the owner's delay. Under many contracts, concurrent contractor delay on the controlling path turns a compensable extension into excusable time only, and an analysis that hides its own side loses credibility everywhere. Deal with it first, on the record, and you control that conversation.

Entitlement in plain terms

Contracts differ, so read yours, but there are usually three buckets:

  • Excusable and compensable. Owner-caused: changes, late design, denied access, owner-furnished equipment slipping. Time plus extended cost, when the TIA shows critical path impact.
  • Excusable, not compensable. Neither party's fault, unusually severe weather being the classic. Time, no money, and the weather has to beat what the contract assumes.
  • Non-excusable. Yours. No time, and the reviewer will test every day you put elsewhere. The contemporaneous record keeps your events out of it.

Float sits under all of it. Most modern contracts say total float belongs to the project, so an event earns an extension only when it drives the path critical. Log float consumption in the update narratives every month, because the change that finally moves completion is proven by the record of float eaten before it. The compounding we covered for subs in the change order release article runs against you from the owner's side. Same cure: evaluate time on every change, not just the big ones.

DRIVING PATH · TOTAL FLOAT BURN-DOWNUPD 1-8 · CDs
+40+200-20 TF = 0 CO 004 · -9 TF CO 011 · -8 TF CO 019 · GOES CRITICAL U1U2U3U4U5U6U7U8 The trajectory shows the cumulative schedule effect. Entitlement also depends on responsibility, notice, concurrency and the contract. WINDOW DECOMPOSITION · COMPLETION MOVEMENT PER UPDATE · PROGRESS VS IMPACT CONTRACTOR PROGRESS IMPACT U1U2U3U4U5U6U7U8 Status first, save, insert, run again. Two runs per window keep your progress separated from their impact.
Two records of the cumulative effect: the driving-path float burn-down with each CO marked where it hit, and each window's completion movement split into contractor progress versus impact.

Field notes from the review side of the table

  • Split progress from impact. Completion moves for two reasons: your own production and the events you want time for. Status the update to just before the event and save it, then insert the fragnet and run again. The first run sets the pre-event forecast, the second measures the fragnet. Your progress and any concurrent delay still get their own review, done contemporaneously.
  • Chart total float on the driving path, every update. Not the project average. One line with CO markers, kept in the narrative. When it crosses zero, the trajectory is the entitlement argument, and the owner is arguing against their own change log.
  • Mirror your sub and prime paperwork. Time you grant a sub should line up with what you claim upstream for the same event. Give the sub 10 CDs for an owner change and ask the owner for 4, and be ready to explain the difference with milestones, logic and float.
  • Treat a directed recovery schedule as a constructive acceleration flag. If the owner denies a supported extension and directs you to hold the date, that combination has a name and money attached. Log the denial and directive, price the acceleration, and involve your attorney now, not at closeout.
  • Keep a delay log keyed to activity IDs. One line per event: date, activity IDs affected, notice reference, fragnet number, TF consumed, status. Minutes a week. It feeds every TIA package, and if the job goes forensic it becomes the spine of the expert's chronology instead of a reconstruction bill.

The process that makes it routine

  • Notice inside the contract window. Your prime contract's notice clause has teeth too, same as your subs'. The notice letter discipline applies up the chain.
  • Fragnet and TIA while the event is live. Prospective analysis, submitted with or shortly after the change proposal, so the time request travels with the cost proposal.
  • The extension into the contract. Granted time goes into a revised schedule with the fragnet incorporated, keeping the record and the network in sync.
  • Updates that keep the story. Monthly narratives on progress, float consumption and open impacts. If a dispute comes, forensic methods under AACE RP 29R-03 build from that record, and the GC with clean updates starts ahead.

This is the rhythm we run as an outside schedule department for small and mid GCs, from the baseline through the monthly cycle to the fragnets and TIAs when changes hit. The owner has a scheduling consultant reviewing your submissions. The GCs who fare best have one producing them.

Owner change on the table, or LDs being threatened?

Send the change and your current update. We'll run the fragnet, tell you what the network shows, and package the request for the reviewer with the assumptions, math and records.

Frequently asked questions

The owner says our schedule shows we can absorb the change. What now?
That's a float argument, and the answer is in the network. If the TIA shows the change consumes total float without moving completion, most contracts give no extension yet, but the consumption goes on the record in the update narrative. If the owner relies on a stale schedule or ignores the fragnet logic, the analysis is your rebuttal.
Do we need a TIA for small changes?
Run the fragnet even when you expect no impact. Small changes add up to a late job with no single event to blame, and a two-hour analysis per change builds the cumulative record. Skipping it builds the owner's defense.
What if the delay already happened months ago?
A long-past delay is usually analyzed retrospectively with forensic methods under AACE RP 29R-03, from the contemporaneous updates. Doable, but slower, costlier, and only as good as your update record.
How does this defend against liquidated damages?
LDs attach to unexcused delay to completion. Each granted extension moves the contract completion date, and each documented owner impact narrows what the owner can pin on you. A TIA and an updated schedule behind each event build the LD defense before the demand arrives.

Carrying owner delays with nothing on the record yet?

Send the change log and current update. On a 20 minute call we'll go through the events with you, flag the records we'd need and scope the TIA work.