Built to protect the subcontractor in every trade
When the job slips, the GC's cheapest fix is reworking the plan you priced: compressed durations, stacked trades, absorbed float, extended duration you never bid. Mechanical, electrical, plumbing, fire protection, drywall, site or any other trade, we document the changes as they happen so your time and cost request rests on the record.
Has the GC changed the logic you agreed to?
Durations get compressed, finish-to-start ties flip to start-to-start, and staggered trades get stacked in one area. That breaks the bid logic you agreed to and pushes lost productivity, cost and float onto your scope.
How this hits your crews, output and margin: When schedules get compressed →
The other way the schedule costs you: extended duration
Acceleration and stacking squeeze your work in. GC-caused delay stretches it out. A trade that priced 12 months and drags to 18 carries six months the bid never covered. Subs most often forget this one.
Watch both. When either is driven by something outside your control, you may be owed for it.
A forensic eye on your scope, before the job goes sideways
Protect your float from day one
A baseline built to your bid logic, so any later change to durations, sequence or float shows against it.
Keep the contemporaneous record
Monthly updates and narratives that log compression, stacking and delay as they happen, so the argument rests on a dated record, not memory.
Audit the logic and the float
We check for compressed durations, flipped ties, inserted lags and absorbed float, and show where your time went.
Tie delay to time and money
Time impact analysis per AACE RP 52R-06 on change orders and GC-caused delay. Time impact is measured, and cost is documented separately.
Recent subcontractor work
A sample, not a full list. Names withheld, references available on request.
Electrical subcontractor, Charlotte, NC
Schedule and delay evaluation on a multifamily build, focused on the sub's exposure. Reviewed contract milestones and durations and tracked delay pushed down to the trades.
Electrical subcontractor, Chapel Hill, NC
Schedule and delay evaluation of the electrical and fire alarm scope on a stalled multifamily project. TIA on building dry-in and predecessor delays, plus resequencing and acceleration review.
Sports complex, Virginia
Mechanical scope. Baseline plus logic and float protection on an aggressive, fixed-date build.
Questions we get from subs
Think the GC is quietly eating your time?
Send your baseline or latest update. On a 20 minute call we'll walk through what you're seeing and tell you what a float and duration review would check and cost.