Mechanical scheduling consultant for HVAC and piping subs
Your scope is at the mercy of the building. Gear can't set until the pad, openings and rigging path exist. Duct can't hang until coordination is signed and the ceiling is yours. Startup and TAB wait on permanent power you don't control. We build P6 schedules that track your sequence, durations and float, and document it when someone else's delay lands on you.
The constraints that actually drive a mechanical schedule
One “HVAC rough-in” bar can hide procurement, coordination, installation and startup dependencies. Each gate below goes into your CPM, because each can cost you time.
Mechanical absorbs the end of the job
When a job runs late, the finish date rarely moves first. Your window does. Between close-in and turnover is where the GC looks for float, and that's your startup, TAB and commissioning time.
How compression and stacking hit your crews and margin: When schedules get compressed → More on protecting a sub's time: Subcontractor schedule protection →
A scheduler in your corner who has built this scope before
A baseline built to your means and methods
Your bid logic, crew flow, procurement chains and startup durations, on record before anyone edits the plan you priced.
Monthly updates that keep the record
Narratives that log stacking, compression and held areas as they happen, not reconstructed later.
Logic and float audits on the GC schedule
We check for compressed durations, flipped ties and float taken from your scope, and show where your time went.
Time impact analysis on changes and delay
TIA per AACE RP 52R-06 on change orders, held areas and compressed windows. The time request rests on the schedule, and cost is documented separately.
Recent mechanical work
Names withheld, references available on request.
Sports complex, Virginia
Mechanical scope. Baseline plus logic and float protection on an aggressive, fixed-date build.
Mass burn waste-to-energy facility, design-build
Full plant scope: boiler, turbine generator, air cooled condenser, ash handling, and major mechanical, piping and electrical packages. Baseline and updates on the resource and quantity loaded P6 schedule.
Biosolids-to-fertilizer facility, EPC
Biosolids receiving and dryer system, granulation plant, and chemical and ammonia storage, with heavy mechanical, piping and electrical scopes. Baseline and updates, with subcontractor schedules integrated into the CPM master.
Questions we get from mechanical subs
Mechanical subs on data center and power work: see our data center and power EPC scheduling page for cooling plant, startup, and commissioning scheduling.
Is your startup and TAB window quietly disappearing?
Send the GC’s latest update and your bid schedule. Give us 20 minutes on the phone and we'll talk through your startup and TAB window, then lay out what a review covers, how long it takes and what it costs.